DR Failback Procedure ​

Status ​

This document is planned for completion after the June 2026 DR test. The failback procedure will be developed based on lessons learned during the test.

Rationale ​

Failback procedures require understanding the operational characteristics of the DR environment under actual load. The June 2026 DR test will provide critical insights into:

  • Data synchronization requirements for returning to Azure
  • Service cutover coordination and timing
  • DNS and routing changeover procedures
  • Verification steps to confirm Azure environment restoration

These insights will inform a comprehensive, tested failback procedure that accounts for real-world operational constraints.

Timeline ​

  • June 2026: Execute DR test and document findings
  • July 2026: Draft failback procedure based on test results
  • October 2026: Test failback procedure during second DR test
  • November 2026: Finalize procedure with lessons learned from both tests

Document History ​

DateChangeAuthor
March 2026Initial placeholder created pending June 2026 DR testRory